Last week, the first kickoff meeting of this major project took place together with our suppliers and end customers at the power plant site. Statron Austria is looking forward to the new challenges and is supplying not only the high quality energy storage systems from our partner Freqcon, but also the complete grid connection with transformers, medium voltage switchgear and cabling. We look forward to realizing further projects of this kind.
EVN’s most modern and efficient thermal power plant is still an indispensable cornerstone of the security of supply in Lower Austria. In addition to electrical energy, district heating for Gedersdorf and the city of Krems is also generated in Tisza. Currently, the thermal power plant Theiß with 430 MW provides grid stabilization in critical grid situations.
Within the SEKOHS Theiß project, a hybrid energy storage system consisting of a 5 MW battery energy storage system with a usable energy content of 3.5 MWh from Statron and a 5 MW P2H system will be installed on the 110 kV grid level. The energy provided will primarily be made available on the market for balancing power.
Christoph Wappel (Sales AT)
Ruben Vogelsang (CEO)
Martin Rehberger – Projet Leader Statron GmbH, Mike Ritter – Sales Manager Freqcon GmbH, Julien Ernst – Project Leader Freqcon GmbH